Foreword

DL/T 5210 Code for Construction Quality Acceptance and Evaluation of Electric Power Construction includes the following 8 parts:

DL/T 5210.1 Part 1:Civil Work

DL/T 5210.2 Part 2:Boiler Unit

DL/T 5210.3 Part 3:Steam Turbine Generator Units

DL/T 5210.4 Part 4:Instrumentation and Control

DL/T 5210.5 Part 5:P Piping & System

DL/T 5210.6 Part 6:Water Treatment Hydrogen Generation Equipment and System

DL/T 5210.7 Part 7:Welding

DL/T 5210.8 Part 8:Processing Preparation

This Part is the second part of DL/T 5210.

This Part is formulated in accordance with the document-Notification on Issuing 2008 Industry Standard Project Plan(NDRC-Office Industry[2008]No.1242)issued by National Development and Reform Commission of the People's Republic of China.

The contents ofThermal Power Construction Quality Inspection and Evaluation Standard-Boiler Section(Construction Quality[1996]No.111)issued by the Construction Coordination Department of the former Ministry of Power Industry of the People's Republic of China have been used as references during the drafting course of this Part.

Annexes A,B,C,D and E of this Part are normative annexes.

This Part is proposed by China Electricity Council.

This Part is interpreted by Electric Power Industry Thermal Power Construction Standardization Technical Committee.

The chief written corporations of this Part are Tianjin Electric Power Construction Company and Shandong Electric Power Construction No.2 Company.

The participants for writing this Part are Ningxia Electric Power Construction Project Company,Hunan Thermal Power Construction Company,Yunnan Thermal Power Construction Company,Shanghai Power Erection No.2 Company(SPESC)and Sichuan No.3 Electric Power Construction Company.

The main drafters of this Part are Liang Binghai,Zhang Dongmao,Li Jinxi,Wang Hongkui,Wang Yongliang,Chai Xiqiang,Xie Honggang,Jia Guangming,Wang Yanyan,Shang Yuling,Yu Guoqiang,Yao Hongmin,Ou Lixin,Liu Yunpan,Shao Chaozhong and Li Jun.

Translators of this Partin English edition are Tian Xiao,Yang Baixun,Zhang Jianguo,Zhang Xin,Guo Yan and Xie Xiaojun of Xi'an Thermal Power Research Institute Co.,Ltd(TPRI for short).

Reviewers of this Partin English edition are Wang Yueming,Xiao Zhigang,Liu Wenli,Zheng Yugui and Shen Guili.

Thermal Power Construction Quality Inspection and Evaluation Standard-Boiler Section(Construction Quality[1996]No.111)issued by the former Construction Coordination Department of Ministry of Electric Power Industry of the People's Republic of China will become invalid since the implementation date of this Part.

Any comments and suggestions during the execution of this Partis are welcomed to feed back to the Standardization Center of China Electricity Council(Address:No.1,Lane 2,Baiguang Road,Beijing;Postcode:100761).