
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人
4.3 General Standards
4.3.1 Scope:the quality acceptance of the erection project of pipes for the thermal power plants.Visual examination and cleaning of pipes is shown in Table 4.3.1-1,The prefabrication of pipes is shown in Table 4.3.1-2.The inspection and erection of valves is shown in Table 4.3.1-3.
4.3.2 Inspection quantity:detailed inspection shall be carried out according to the items.
4.3.3 Quality criteria:in accordance with the requirements in Table 4.3.1-1 to Table 4.3.1-3.
Table 4.3.1-1 Visual examination and cleaning of pipes

Table 4.3.1-1(Continued)

Table 4.3.1-2 Prefabrication of pipes

Table 4.3.1-3 Inspection and erection of valves
